Construction of electromechanical installations and 20/150kV substations (1×40/50 MVA) in the following locations:
Ano Pyxarion, Nikiforos Municipality, Drama
Ano Pyxarion, Nikiforos Municipality, Drama
Angelokastro, Midea Municipality, Argolida
Works include installation of 20/150kV transformers, MV/LV panels, outdoor junction boxes, cable termination, substation grounding, cable trays, lighting, supports, testing, and commissioning.